Gorham school bids over estimate

BLADE STAFF

FAYETTE - Bids for the largest projects in constructing the new Gorham Fayette Local school, which are expected to be formally considered by the board of education on Dec. 18, came in over estimate.

There also were not as many bids, particularly for plumbing and electrical work, as construction managers had anticipated, according to Superintendent Dave Hankins.

Opened on Friday were:

•Four bids for general trades, ranging from $8.3 million to $8.7 million. The estimate was $7.7 million.

•Two bids for electrical work, ranging from $1.7 million to $1.9 million. The estimate was $1.5 million.

•Three bids for heating, ventilation, and air conditioning ranging from $1.3 million to $1.4 million. The estimate was $1.8 million.

•Two bids for plumbing, ranging from $558,000 to $615,000. The estimate was $721,000.

•Four bids for fire suppression, ranging from $253,000 to $283,000. The estimate was $245,000.



Guidelines: Please keep your comments smart and civil. Don't attack other readers personally, and keep your language decent. If a comment violates these standards or our privacy statement or visitor's agreement, click the "X" in the upper right corner of the comment box to report abuse. To post comments, you must be a Facebook member. To find out more, please visit the FAQ.